Project Information

23 m deep excavation is supported by 800 mm thick Diaphragm Walls and Pre-Stressed Anchors. Shotcrete is applied where the bedrock rises. Bored piles and Double Corrosion Protection (DCP) micropiles were applied under the foundations of the structure. Groundwater was drained with deep wells built in the pit.

 

 

 

0m2
Diaphragm Wall
0m
Pre-stressed Anchor

Employer:
Orjin Gayrimenkul Yatırım İnsaat A.Ş.

Project:
İzmir İstinye Park Project

 

Country:
Turkey

Year:
2017

Related Techniques

Related Projects

Work with us

 

We at ZETAŞ, are able to provide our customers with top-notch design and value engineering thanks to our highly educated engineers in addition to our experience in contracting.